整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-567

题目

你在做一个超高空无人机项目。执行期间技术负责人说他们改了导航系统,让无人机飞得更快更高,但项目文件中毫无记录。你应当立即做什么?
You lead a project to build ultra-high-altitude drones. During execution, your technical lead says they changed the navigation system so the drone can fly faster and higher. Project documents show no evidence of this capability. What should you do immediately?

选项

  1. A.Inform the project sponsor of the new flight capabilities
  2. B.Update the project development approach to better manage changes
  3. C.Record the change in the change log
  4. D.Recommend that the technical lead will be rewarded for their effort
正确答案:C

解析

解析:无论批准、否决还是推迟,所有变更都必须记入变更日志,这是整体变更控制的要求。先留痕,再谈其他动作。 Rationale:All changes, approved, denied or postponed, must be recorded in the change log as part of integrated change control. Documentation comes before any other action.