题目
某新疫苗项目中,一名成员认为发现了更优方案,提交变更请求以获取额外材料做小规模实验。项目经理首先应当做什么?
On a project to develop a new vaccine, a team member thinks she has discovered an approach that would yield better results and submits a change request for additional material to run a small experiment. What should the PM do first?
选项
- A.Have the members of the change control board decide on the change request
- B.Update project documents affected using the configuration management plan
- C.Instruct the team to implement the change since the new vaccine may save lives
- D.Make sure the impact of the change request on project constraints is analyzed
解析
解析:变更请求提交后,必须先分析其对范围、进度、成本、质量与风险的影响,CCB 或授权人才能据此决策。
Rationale:A submitted change request must be analyzed for impact on scope, schedule, cost, quality and risk before the CCB or authorized individual decides.
同考点练习题
-
PMP202611-006 · 答案 B
-
PMP202611-031 · 答案 C
-
PMP202611-056 · 答案 C
-
PMP202611-066 · 答案 B
-
PMP202611-093 · 答案 D
-
PMP202611-116 · 答案 B
-
PMP202611-125 · 答案 B
-
PMP202611-191 · 答案 B