整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-566

题目

某新疫苗项目中,一名成员认为发现了更优方案,提交变更请求以获取额外材料做小规模实验。项目经理首先应当做什么?
On a project to develop a new vaccine, a team member thinks she has discovered an approach that would yield better results and submits a change request for additional material to run a small experiment. What should the PM do first?

选项

  1. A.Have the members of the change control board decide on the change request
  2. B.Update project documents affected using the configuration management plan
  3. C.Instruct the team to implement the change since the new vaccine may save lives
  4. D.Make sure the impact of the change request on project constraints is analyzed
正确答案:D

解析

解析:变更请求提交后,必须先分析其对范围、进度、成本、质量与风险的影响,CCB 或授权人才能据此决策。 Rationale:A submitted change request must be analyzed for impact on scope, schedule, cost, quality and risk before the CCB or authorized individual decides.