质量管理 中等 Process 过程域 题号 PMP202611-568

题目

各团队都执行质量管理计划,但质量活动几乎都集中在“有效使用流程”上,很少投入产品设计与流程改进。你应当建议什么?
Project teams follow their quality management plans, but almost all quality activities focus on effective use of project processes with very little time on product design and process improvement. What should you recommend?

选项

  1. A.Focus on the quality assurance activities rather than on the Manage Quality process
  2. B.Focus on the Manage Quality process rather than on quality assurance activities
  3. C.Increase the budget allocated to team members for rewards and recognition
  4. D.Outsource all quality management related activities to external vendors
正确答案:B

解析

解析:管理质量的范围大于质量保证:它既包含质量保证活动,也覆盖设计层面与流程改进。该组织目前只做了其中一小块。 Rationale:Manage Quality encompasses quality assurance activities plus design considerations and process improvement. The organization is only covering the assurance slice.