整合管理 困难 Process 过程域 题号 PMP202611-553

题目

项目接近尾声时,项目经理收到一份已批准的变更请求,要求更换一台有缺陷的设备。下一步应当做什么?
A project is nearing its end when the project manager receives an approved change request to replace a defective unit. What should the project manager do next?

选项

  1. A.Capture the problem in the issue log
  2. B.Meet with the change control board
  3. C.Have the defective unit repaired
  4. D.Have the defective unit replaced
正确答案:D

解析

解析:已批准的变更请求是“指导与管理项目工作”的输入,项目经理的职责就是按请求内容落实——本例即执行更换。 Rationale:Approved change requests are inputs to Direct and Manage Project Work; the PM's responsibility is to ensure they are implemented as specified — here, replacing the unit.