题目
项目接近尾声时,项目经理收到一份已批准的变更请求,要求更换一台有缺陷的设备。下一步应当做什么?
A project is nearing its end when the project manager receives an approved change request to replace a defective unit. What should the project manager do next?
选项
- A.Capture the problem in the issue log
- B.Meet with the change control board
- C.Have the defective unit repaired
- D.Have the defective unit replaced
解析
解析:已批准的变更请求是“指导与管理项目工作”的输入,项目经理的职责就是按请求内容落实——本例即执行更换。
Rationale:Approved change requests are inputs to Direct and Manage Project Work; the PM's responsibility is to ensure they are implemented as specified — here, replacing the unit.