结束项目与阶段收尾 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-552

题目

某原型建造项目分三阶段:设计、制造零件、装配。目前第一阶段即将结束。该阶段交付物应当如何处理?
A three-phase project to build a prototype is underway: design, manufacturing parts, then assembly. The project is now at the end of the first phase. What should be done with the phase's deliverables?

选项

  1. A.Verified by the testing team for quality compliance
  2. B.Transferred to the production team
  3. C.Transitioned to the project management office (PMO)
  4. D.Handed over to the manufacturing team
正确答案:D

解析

解析:阶段收尾的一项重要输出,是把成果移交给后续负责运营或支撑的团队。设计成果应移交制造团队,因为第二阶段由他们负责。 Rationale:Closing a phase includes transitioning the product, service or result to the group that will operate or support it. Design ownership transfers to the manufacturing team, which runs the second phase.

同考点练习题