整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-551

题目

组织规定所有项目的变更请求都必须由变更控制委员会(CCB)评审,且项目经理与团队成员不得进入 CCB。按此情形,下列哪项活动可能由 CCB 成员执行?
An organization requires a CCB to review all change requests for every project, and PMs and team members are not allowed to be part of the CCB. Based on this scenario, which of the following activities might be performed by members of the CCB?

选项

  1. A.Submitting a change request
  2. B.Implementing approved change requests
  3. C.Initiating and closing a project
  4. D.Monitoring implementation of approved changes
正确答案:A

解析

解析:CCB 负责评审、评估、批准、推迟或否决变更请求。CCB 可由相关方组成,任何相关方都可提出变更,因此 CCB 成员也可以提交变更请求。 Rationale:The CCB reviews, evaluates, approves, defers or rejects change requests. The CCB can include project stakeholders, and any stakeholder may request a change — so a CCB member can submit one.

同考点练习题