题目
需求评估与商业论证已完成,PMO 正在评审效益管理计划草案,并指出其中一项应删除。最可能被要求删除的是哪一项?
A needs assessment and business case have been completed, and the PMO is reviewing a draft of the benefits management plan. The PMO highlights an element and requests that it be removed before the document is finalized. Which element was most likely requested for removal?
选项
- A.Expected tangible and intangible value to be gained by the implementation of the project
- B.A set of options to be considered for addressing the business opportunity
- C.A timeframe for realizing the benefits of the project
- D.Measures to be used to show benefits realized
解析
解析:效益管理计划包含目标效益、战略对齐、实现时限、效益负责人、度量指标、假设与风险。“备选方案集合”属于商业论证的内容,不应出现在效益管理计划中。
Rationale:The benefits management plan includes target benefits, strategic alignment, timeframe, benefits owner, metrics, assumptions and risks. A set of options for addressing the business opportunity belongs in the business case, not here.