题目
项目经理在为其第一个敏捷项目的回顾会做引导。成员各自埋头完成由项目经理分派的任务,结果项目延期且超支,团队意识到大量返工导致了失败。项目经理本可以怎样做?
A project manager is facilitating a retrospective for his first agile project. Team members worked individually and diligently on tasks assigned by the project manager, yet the project finished late and over budget. The team realizes excessive rework caused the miss. What might the project manager have done differently?
选项
- A.Increased the work in progress (WIP) limits on the team's Kanban board
- B.Increased the number of developers on the project team
- C.Established a war room for the project team to work collaboratively
- D.Established a more robust change control process
解析
解析:敏捷团队应自组织并按协作方式工作,而不是被逐项分派任务。各自孤立作业,问题只在集成时才暴露,返工不可避免;协作环境能让工作近乎实时对齐。
Rationale:Agile teams should be self-organizing and collaborate rather than receiving task assignments. Working in isolation meant issues surfaced only at integration, causing rework; a collaborative environment aligns work in near real time.