题目
在辅导表现不佳的团队成员时,项目经理应重点关注:
When coaching an underperforming team member, the project manager should focus on:
选项
- A.Highlighting performance issues publicly
- B.Providing constructive feedback and identifying improvement areas
- C.Reducing their responsibilities permanently
- D.Assigning only low-risk work
解析
解析:辅导与指导能帮助团队成员提升绩效,同时维护其积极性和信任关系。
Rationale:Coaching and mentoring help team members improve performance while maintaining motivation and trust.