题目
你的团队因外部依赖而受阻。项目经理的角色是什么?
Your team is blocked by an external dependency. What is the project manager’s role?
选项
- A.Ask the team to resolve it themselves
- B.Remove the blocker for the team
- C.Log the risk and wait for the sponsor
- D.Pause the sprint
解析
解析:项目经理或服务型领导的核心职责之一,就是清除阻碍团队前进的障碍。
Rationale:One of the key responsibilities of a project manager or servant leader is removing obstacles that slow down the team.