领导力风格与团队激励 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-227

题目

两个需要集成工作的团队开始相互竞争而非合作,各自守着自己的范围。项目经理最有效的行动是什么?
Two teams that must integrate their work have started competing instead of cooperating, each protecting its own scope. What is the most effective action by the project manager?

选项

  1. A.Let the stronger team set the integration approach.
  2. B.Create shared goals and joint planning so both teams succeed together.
  3. C.Keep the teams apart and integrate only at the end.
  4. D.Have each team report the other's shortcomings to you.
正确答案:B

解析

解析:共同目标与联合规划能对齐激励,使合作优于竞争,体现系统观。让一方主导会积累怨气;只在末端集成则会最大化不兼容风险。 Rationale:Shared goals and joint planning align incentives so cooperation beats competition, reflecting a systems view. Letting one team dominate breeds resentment; integrating only at the end maximises incompatible work.