相关方管理 中等 People 人域 题号 PMP202611-147

题目

项目经理正在为某研究项目识别相关方,涵盖学术界、产业界与政府部门人士。相关方识别完成后,项目经理应该做什么?
A project manager is identifying stakeholders for a research project. The stakeholders include individuals from academia, industry, and government. What should the project manager do once stakeholders are identified?

选项

  1. A.Communicate with the stakeholders about the progress of the project on a regular basis
  2. B.Conduct facilitation sessions with the stakeholders to understand and align their expectations
  3. C.Focus on key stakeholders who are critical to the project
  4. D.Engage the stakeholders based on their influence on the project
正确答案:B

解析

解析:识别相关方之后,项目经理须立即分析其需求、利益与期望,以制定参与计划。面对利益可能冲突的多元群体,应先通过引导式研讨统一期望,再开展沟通与参与。 Rationale:Immediately after identifying stakeholders, the PM must analyze their needs, interests, and expectations to build the engagement plan. With diverse groups holding potentially conflicting interests, facilitated sessions align expectations before communication or engagement begins.