管理相关方参与 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202603-005

题目

一位项目经理正在领导一项涉及现场团队成员的混合项目,用于开发牙科设备。一位牙医,也是主要投资者之一,参加了一个冲刺评审会议,并对设备的概念和预期性能提出了问题和疑虑。项目经理应该怎么做? A project manager is leading a hybridproject for the development of dentalequipment with live team members. Adentist, who is also one of the majorinvestors attends a sprint review meetingand raises questions and doubt about theconcept and expected performance ofthe equipment. What should the project manager do?
一位项目经理正在领导一项涉及现场团队成员的混合项目,用于开发牙科设备。一位牙医,也是主要投资者之一,参加了一个冲刺评审会…

选项

  1. A.邀请投资者参加冲刺回顾会议,与团队讨论改进设备的概念和预期性能。 Invite the investor to a Sprint retrospectivemeeting to discuss the improvements ofthe concept and expected performance of the equipment with the team.
  2. B.邀请项目发起人参加冲刺评审会议,并进行关于设备概念和预期性能的问答环节。 Invite the project sponsor to the sprintreview meeting and have a Q&A sessionabout the concept and expected performance of the equipment.
  3. C.邀请产品负责人和团队讨论设备的概念和预期性能。 Invite product owner and team todiscuss about the concept and expected performance of the equipment.
  4. D.请投资者参加设计评审会议,介绍设备的概念和预期性能,并在会议中进行问答环节。 Invite the investor to the design review meeting to present the concept and expected performance of the equipment, and include a Q&A session in the meeting.
正确答案:D

解析

解析:选项最佳,根据题干,项目经理应邀请牙医参加设计评审会议,在会议中他可以详细了解设备的设计和预期性能,会议中的问答环节也能提供消除疑虑的机会。选项 A 错误,冲刺回顾是团队反思过去冲刺并确定下一次冲刺改进的会议。

同考点练习题