题目
项目团队正在审查项目的商业文件以进行阶段关口会议,并发现效益需要由项目发起人验证。不幸的是,项目的发起人最近被更换,新的发起人似乎并不支持。项目经理应该如何应对这种情况?
A project team is reviewing the projectbusiness document for a phase-gatesession and discovers that the benefitsneed to be validated by the projectsponsor. Unfortunately, the projectsponsor was recently changed, andthe new sponsor does not seem to besupportive. What should the project
manager do to address this situation?

选项
- A.通知并上报到高层管理团队,要求他们采取行动。 Notify and escalate to the high-levelmanagement team and request that they take action.
- B.项目发息人安排讨论,澄清项目的商业文件。 Arrange for a discussion with the projectsponsor and clarify the project business document.
- C.安排与项目发起人的一对一会议,以获得他们对项目效益的支持。 Schedule a one-on-one meeting with theproject sponsor to obtain their buy-in on the project benefits.
- D.在风险登记册中添加管理层更迭的风险。 ldentify and add the change inmanagement as a risk in the risk register.
解析
题干分析:
项目正处于阶段关口会议准备期,核心任务是审查商业文件并验证效益。此时关键相关方(发起人)变更且表现出不支持态度,这直接影响项目能否通过关口。项目经理的首要任务是解决相关方对齐问题,确保对项目商业价值的理解一致。
选项分析:
- A 选项:上报高层通常是最后手段。项目经理应先尝试直接与相关方沟通解决问题,直接上报显得缺乏解决问题的能力。
- B 选项:正确。既然问题出在“商业文件审查”和“效益验证”上,且发起人不支持,最直接的做法是与发起人讨论,澄清商业文件内容,确保双方对项目目标和效益的理解一致,从而争取支持。
- C 选项:虽然目的是获得支持,但相比 B 选项,它略显空泛。在不理解发起人不支持的根本原因(可能是对商业文件误解)之前,直接要求“获得支持”可能无效。B 选项的“澄清文件”是获得支持的具体手段。
- D 选项:记录风险是被动的。这是一个已经发生的阻碍项目进展的问题(Issue),需要主动解决,而不仅仅是记录风险。
知识点说明:
本题考查相关方参与管理和项目商业文件的作用。在阶段关口,商业文件(如商业论证、效益管理计划)是决策依据。当关键相关方变更时,重新对齐商业目标至关重要。