题目
一位关键相关方持续缺席评审会议,且两项关键可交付成果一直未获批准,导致进度延误。项目经理已多次发邮件但无回应。项目经理应该怎么做?
A key stakeholder consistently misses review meetings and has not approved two critical deliverables, causing schedule delays. The project manager has sent multiple emails without response. What should the project manager do?
选项
- A.Proceed with the project without the stakeholder's approval to avoid further delays.
- B.Meet with the stakeholder directly, understand why they are disengaged, and work with the sponsor to define a clear escalation path if approvals continue to be missed.
- C.Escalate immediately to the project sponsor and request that they force the stakeholder to respond.
- D.Document the delays caused by the stakeholder and update the risk register.
解析
解析:B 正确。PMI 要求主动管理相关方参与。直接面谈常能发现其不投入的真正原因(太忙、并非正确审批人、期望不清),并据此解决。与发起人共同建立升级路径,为后续不响应提供正式机制。无审批就推进(A)带来范围风险;立即上报(C)跳过沟通且可能损害关系;仅记录(D)不能解决问题。
Rationale:B is correct. PMI expects proactive stakeholder engagement. A direct conversation often reveals the reason for disengagement (too busy, not the right approver, unclear expectations) which can be resolved. Working with the sponsor to create an escalation path establishes a formal mechanism for future non-responses. Proceeding without approval (A) creates scope risk. Immediate escalation (C) skips the direct conversation and may damage the relationship. Documentation alone (D) does not resolve the issue.