题目
财务负责人认为你的项目会削减其部门预算,已开始阻挠审批。最好的处理方式是什么?
The finance head believes your project will reduce their department's budget and has started to block approvals. What is the best way to handle this?
选项
- A.Ask the sponsor to order the finance head to cooperate.
- B.Meet the finance head to understand their concerns and update the stakeholder engagement plan.
- C.Leave the finance head out of future communications.
- D.Proceed without their approvals.
解析
解析:抵触型相关方需要主动参与。了解其顾虑有助于找到共同点,并规划如何将其转为支持者。排除或绕过对方通常会加剧抵触。
Rationale:Resistant stakeholders need active engagement. Understanding their concerns helps you find common ground and plan how to move them toward support. Excluding them or going around them usually increases resistance.