题目
案例背景同上。新的医疗隐私法规可能要求平台在上线前做出调整。项目经理下一步应当做什么?
Case study: new healthcare privacy regulations may require modifications to the platform before deployment. What should the project manager do next?
选项
- A.Begin implementing the compliance enhancements while the requirements are being finalized.
- B.Work with compliance to assess the regulatory impact and identify any required project changes.
- C.Escalate the issue to the steering committee so they can determine whether the project should continue.
- D.Work with the development team to prepare a technical spike and impact analysis for the likely compliance changes.
解析
解析:先与合规专家一起弄清法规到底要求什么,再决定项目是否要改。法规是硬约束而非可协商的请求,问题从来不是“要不要遵守”,而是“遵守具体意味着什么”。
Rationale:First collaborate with compliance experts to understand the regulation's impact before deciding whether changes are necessary. Regulatory requirements are constraints, not negotiable requests.
同考点练习题
-
PMP202611-208 · 答案 B
-
PMP202611-217 · 答案 C
-
PMP202611-334 · 答案 C
-
PMP202611-452 · 答案 B
-
PMP202611-468 · 答案 C
-
PMP202611-525 · 答案 D
-
PMP202611-652 · 答案 A