合规管理与法规遵循 · PMP 练习题解析

职业道德与合规 困难 Business Environment 商业环境域 题号 PMP202611-542

题目

案例背景同上。新的医疗隐私法规可能要求平台在上线前做出调整。项目经理下一步应当做什么?
Case study: new healthcare privacy regulations may require modifications to the platform before deployment. What should the project manager do next?

选项

  1. A.Begin implementing the compliance enhancements while the requirements are being finalized.
  2. B.Work with compliance to assess the regulatory impact and identify any required project changes.
  3. C.Escalate the issue to the steering committee so they can determine whether the project should continue.
  4. D.Work with the development team to prepare a technical spike and impact analysis for the likely compliance changes.
正确答案:B

解析

解析:先与合规专家一起弄清法规到底要求什么,再决定项目是否要改。法规是硬约束而非可协商的请求,问题从来不是“要不要遵守”,而是“遵守具体意味着什么”。 Rationale:First collaborate with compliance experts to understand the regulation's impact before deciding whether changes are necessary. Regulatory requirements are constraints, not negotiable requests.