Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-539

题目

回顾会上一名健谈者主导发言,其他人沉默。Scrum Master 应当:
During a retrospective, one vocal member dominates while others stay silent. The Scrum Master should:

选项

  1. A.End the retrospective early
  2. B.Ask the vocal member to leave
  3. C.Skip retrospectives for a few sprints
  4. D.Use structured techniques like round-robin or silent writing to give everyone voice
正确答案:D

解析

解析:轮流发言、静默头脑风暴等引导技术能保证参与均衡、维护心理安全。 Rationale:Facilitation techniques such as round-robin or silent brainstorming ensure balanced participation and psychological safety.