相关方分析与权力利益方格 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-538

题目

对影响力高但关注度低的相关方,应采用哪种管理策略?
A stakeholder with high influence but low interest in the project should be managed by which strategy?

选项

  1. A.Keep them closely managed
  2. B.Monitor with minimal effort
  3. C.Keep them satisfied
  4. D.Keep them informed
正确答案:C

解析

解析:高权力低关注者要“让其满意”:投入足以维持支持,又不至于打扰过度。 Rationale:High power/low interest stakeholders should be kept satisfied — enough engagement to maintain support without overwhelming them.