题目
敏捷团队与预测型团队需每月集成交付物,但集成屡屡失败。最佳结构性解法是:
An agile team and a predictive team must integrate deliverables monthly. Integration keeps failing. The BEST structural fix is to:
选项
- A.Hold more meetings
- B.Let each team integrate whenever ready
- C.Merge the teams into one methodology
- D.Define a shared integration cadence with agreed interface contracts and a joint integration owner
解析
解析:混合集成需要结构性安排:共同节奏、接口契约与清晰的集成责任人。
Rationale:Hybrid integration needs structure: shared cadence, interface contracts, and clear ownership of integration.