效益实现主要确保:
Benefits realization primarily ensures that:
选项
- A.The project finishes early
- B.The team gets bonuses
- C.Stakeholders attend meetings
- D.The project delivers the value and outcomes justified in the business case
解析
解析:效益实现跟踪的是项目最终是否真的兑现了立项时承诺的业务价值。
Rationale:Benefits realization tracks whether the project actually delivers the business value promised in its justification.