团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-529

题目

与新接手的项目团队建立信任,最佳方式是:
The BEST way to build trust with a newly assigned project team is to:

选项

  1. A.Be transparent, keep commitments, and show respect for expertise
  2. B.Set aggressive deadlines immediately
  3. C.Share all sponsor emails with the team
  4. D.Work longer hours than everyone else
正确答案:A

解析

解析:信任来自透明、可靠与尊重,而不是施压或拼工时。 Rationale:Trust is built through transparency, reliability, and respect — not through pressure or overwork.