成本管理 中等 Process 过程域 题号 PMP202611-524

题目

效益负责人的职责是:
A benefits owner is accountable for:

选项

  1. A.Writing code
  2. B.Ensuring planned benefits are actually realized after delivery
  3. C.Scheduling meetings
  4. D.Approving timesheets
正确答案:B

解析

解析:效益负责人跟踪业务效益的落地,这项工作常在项目收尾之后仍持续。 Rationale:The benefits owner tracks realization of business benefits, often after the project closes.