在绩效评估中,项目经理的最佳反馈方式是:
During performance reviews, the BEST feedback approach for a project manager is:
选项
- A.Timely, specific, behavior-focused feedback given regularly
- B.Annual formal reviews only
- C.Only positive feedback to keep morale high
- D.Feedback delivered through the functional manager
解析
解析:及时、具体、对事不对人且常态化的反馈,效果远胜偶尔一次的正式评估。
Rationale:Timely, specific, behavior-focused feedback given regularly is far more effective than infrequent formal reviews.