团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-510

题目

项目团队的基本规则应当:
Ground rules for a project team should be:

选项

  1. A.Imposed by the sponsor
  2. B.Established collaboratively with the team
  3. C.Copied from another project unchanged
  4. D.Avoided to keep things flexible
正确答案:B

解析

解析:共同制定的规则才有团队认同,被遵守的概率高得多。 Rationale:Collaboratively established ground rules gain team buy-in and are far more likely to be followed.