题目
冲刺中途生产环境发现严重缺陷,产品负责人要求立刻修,而团队正在冲刺中。最佳做法是:
Mid-sprint, a critical defect is found in production. The product owner wants it fixed now; the team is mid-sprint. BEST action:
选项
- A.Finish the sprint first, then fix
- B.Assess severity with the PO; if truly critical, the PO may cancel the sprint and replan — otherwise add to backlog
- C.Ignore the defect
- D.Work overtime without telling anyone
解析
解析:只有产品负责人能取消冲刺;确属致命问题才值得取消,否则缺陷进待办按优先级排队。
Rationale:Only the product owner can cancel a sprint; critical production issues may justify it, otherwise the defect joins the backlog by priority.