Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-509

题目

冲刺中途生产环境发现严重缺陷,产品负责人要求立刻修,而团队正在冲刺中。最佳做法是:
Mid-sprint, a critical defect is found in production. The product owner wants it fixed now; the team is mid-sprint. BEST action:

选项

  1. A.Finish the sprint first, then fix
  2. B.Assess severity with the PO; if truly critical, the PO may cancel the sprint and replan — otherwise add to backlog
  3. C.Ignore the defect
  4. D.Work overtime without telling anyone
正确答案:B

解析

解析:只有产品负责人能取消冲刺;确属致命问题才值得取消,否则缺陷进待办按优先级排队。 Rationale:Only the product owner can cancel a sprint; critical production issues may justify it, otherwise the defect joins the backlog by priority.