效益实现与价值管理 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-491

题目

某项目效益预期每年 200 万美元,实际跟踪只有 80 万。效益负责人应当:
A project benefit was projected at $2M/year but realization tracking shows $800K. The benefits owner should:

选项

  1. A.Hide the shortfall
  2. B.Report honestly, analyze causes, and propose corrective actions to the sponsor
  3. C.Cancel the project retroactively
  4. D.Blame the project manager
正确答案:B

解析

解析:效益实现需要诚实汇报与纠正行动,效益负责人的职责是抢救价值而不是遮掩。 Rationale:Benefits realization requires honest reporting and corrective action — the benefits owner drives value recovery, not concealment.