题目
敏捷团队持续达不到承诺的故事点数。最佳应对是:
Your agile team consistently delivers fewer story points than committed. The BEST response is to:
选项
- A.Add more people to the team
- B.Require overtime
- C.Use the team's demonstrated velocity for future planning and investigate impediments
- D.Reduce quality standards
解析
解析:按真实速率规划并解决障碍;加人或加班通常治不了系统性的产能问题。
Rationale:Plan using actual velocity and address impediments; adding people or overtime rarely fixes systemic throughput issues.
同考点练习题
-
PMP202611-259 · 答案 D
-
PMP202611-284 · 答案 B
-
PMP202611-313 · 答案 C
-
PMP202611-333 · 答案 B
-
PMP202611-394 · 答案 B
-
PMP202611-453 · 答案 C
-
PMP202611-474 · 答案 C
-
PMP202611-497 · 答案 A