敏捷与混合实践 困难 Process 过程域 题号 PMP202611-492

题目

敏捷团队持续达不到承诺的故事点数。最佳应对是:
Your agile team consistently delivers fewer story points than committed. The BEST response is to:

选项

  1. A.Add more people to the team
  2. B.Require overtime
  3. C.Use the team's demonstrated velocity for future planning and investigate impediments
  4. D.Reduce quality standards
正确答案:C

解析

解析:按真实速率规划并解决障碍;加人或加班通常治不了系统性的产能问题。 Rationale:Plan using actual velocity and address impediments; adding people or overtime rarely fixes systemic throughput issues.