题目
防止范围蔓延的最佳方式是:
Scope creep is BEST prevented by:
选项
- A.Working faster
- B.Hiring more staff
- C.A defined scope statement plus integrated change control
- D.Skipping planning
解析
解析:清晰的范围说明书划定边界,整体变更控制则对每个提议的变更先评估再批准。
Rationale:A clear scope statement defines boundaries; integrated change control evaluates every proposed change before approval.