范围控制与变更处理 · PMP 练习题解析

范围管理 中等 Process 过程域 题号 PMP202611-174

题目

一名开发人员擅自增加了一个客户从未要求的仪表盘,以为这样能让客户满意。你应该怎么做?
A developer adds an extra dashboard the customer never asked for, thinking it will impress them. What should you do?

选项

  1. A.Show it to the customer as a bonus.
  2. B.Explain that unrequested work is not in scope and must go through the change process if needed.
  3. C.Thank the developer and add it to the release.
  4. D.Remove the developer from the team.
正确答案:B

解析

解析:镀金会在未获批准的情况下增加成本、风险和测试工作量。未请求的功能必须走变更控制;同时辅导该开发人员以防再次发生。 Rationale:Gold plating adds cost, risk and testing effort without approval. Unrequested features must go through change control; coaching the developer prevents a repeat.