范围管理 中等 Process 过程域 题号 PMP202611-308

题目

项目执行中出现范围蔓延:大量未经批准的小改动累积起来,已威胁到进度。对未来项目而言,最好的预防措施是什么?
During project execution, scope creep is occurring: small, unapproved additions have accumulated to the point where the schedule is at risk. What is the BEST preventive measure for future projects?

选项

  1. A.Reject all scope changes regardless of their value to maintain baseline control.
  2. B.Increase contingency reserves to absorb the impact of scope creep.
  3. C.Establish a robust scope management plan with a clearly defined change control process, and educate all stakeholders on the process from project initiation.
  4. D.Assign a dedicated team member to monitor and reject all change requests.
正确答案:C

解析

解析:C 正确。范围蔓延最好通过主动的范围管理来预防:清晰基准、被理解的变更控制流程,以及从启动就被宣贯、明白流程意义的相关方。专人拒绝变更(D)会制造对立;一概拒绝(A)僵化且可能错过有价值的改进;增加储备(B)只是消化财务影响,并不预防问题。 Rationale:C is correct. Scope creep is best prevented through proactive scope management: a clear baseline, an understood change control process and educated stakeholders who know why the process exists. A dedicated change rejector (D) creates adversarial dynamics. Rejecting all changes (A) is inflexible and may miss valuable improvements. Increasing reserves (B) absorbs the financial impact but doesn't prevent the problem.