案例背景:某混合模式的云医疗平台项目,已交付多个版本。一位高管要求在计划上线前增加“AI 病历摘要”功能,但该功能不在已批准范围内,也未追加预算或工期。项目经理首先应当做什么?
Case study: a hybrid cloud healthcare platform project. A senior executive requests that an AI patient-summary feature be included before the planned product launch. What should the project manager do first?
选项
- A.Ask the product owner to evaluate whether lower-value features could be deferred to make room for the request.
- B.Approve development immediately because the feature provides significant business value.
- C.Submit a change request to evaluate the impacts before making any commitment.
- D.Recommend delivering the feature after the initial release to avoid disrupting the current schedule.
解析
解析:功能再有价值也属范围外变更,必须先走变更控制评估影响。高管的影响力不等于授权;只有正式的变更请求才能产出决策所需的分析。混合项目仍有基准——在批准范围内重排待办是正常的,追加从未授权的功能则必须走整体变更控制。
Rationale:Although the feature may provide business value, it is outside the approved scope. The PM should follow change control and evaluate impacts before committing. Influence is not authorization; a documented change request produces the analysis decision makers need.