管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-489

题目

两位资深开发在架构上意见相左,双方观点都合理且决策紧迫。此处最佳的冲突解决方式是:
Two senior developers disagree on architecture. Both have valid points and the decision is urgent. The BEST conflict resolution technique here is:

选项

  1. A.Collaborating
  2. B.Smoothing
  3. C.Forcing
  4. D.Withdrawing
正确答案:A

解析

解析:合作/解决问题能吸收双方视角找到最优解,适合决策重要且两种观点都有道理的情形。 Rationale:Collaborating (problem-solving) incorporates both perspectives to find the best solution — ideal when the decision is important and both views have merit.