题目
某混合型项目的团队给出了估算,但所有估算都被低估。按当前趋势,项目将在预算耗尽前无法实现预期价值。项目经理应该怎么做?
A project team provided estimates for a hybrid project, but in every case the estimates were undervalued. On the current trajectory, the project will not meet its intended value before it runs out of budget. What should the project manager do?
选项
- A.Review the number of sprints remaining and update estimates using planning poker
- B.Convert the project to a pure agile approach and enforce sprint planning
- C.Re-estimate the remaining project tasks and submit a change request
- D.Monitor the budget variations to work with the governance process
解析
解析:混合项目的预算基准仍按预测型治理。项目经理应重新估算剩余工作以计算完工尚需估算,再向 CCB 或发起人提交正式变更请求,以调整基准、追加资金或协商削减范围。仅监控或只做敏捷层面的修补都无法解决基准缺口。
Rationale:In a hybrid project the budget baseline is still governed predictively. The PM recalculates Estimate to Complete by re-estimating remaining work, then submits a formal change request to the CCB or sponsor to adjust the baseline, secure funding, or negotiate reduced scope. Monitoring or agile-only fixes do not resolve the baseline deficit.