题目
项目执行中途必须遵守新的数据隐私法规,该法规强制且不可协商。最佳做法是:
Your project must comply with new data-privacy regulations mid-execution. The regulation is mandatory and non-negotiable. The BEST approach is to:
选项
- A.Treat it as a risk and hope for the best
- B.Ignore it until project close
- C.Ask the team to work around it informally
- D.Raise a change request, assess compliance impact, and integrate required changes via change control
解析
解析:法规强制要求走正规变更控制:评估影响、取得批准、把合规要求并入计划。
Rationale:Regulatory mandates require formal change control: assess impact, get approval, and integrate compliance into the plan.