卖方交付物未通过验收测试。合同为固定总价且含质保条款。最佳做法是:
A vendor's deliverable fails acceptance testing. The contract is fixed-price with a warranty clause. The BEST action is to:
选项
- A.Invoke the warranty clause and require the vendor to correct the defects
- B.Accept it and fix it internally
- C.Terminate the contract immediately
- D.Pay a bonus to speed up fixes
解析
解析:质保条款在合同上要求卖方纠正缺陷,启用该条款才是正当救济手段。
Rationale:The warranty clause contractually obligates the vendor to correct defects; invoking it is the proper remedy.