题目
项目中的合规要求是:
Compliance requirements in a project are:
选项
- A.Optional guidelines
- B.Suggestions from the team
- C.Mandatory obligations that must be met, often from laws or regulations
- D.Marketing claims
解析
解析:合规事项没有商量余地,源自法律、法规或有约束力的政策。
Rationale:Compliance items are non-negotiable — they stem from laws, regulations, or binding policies.