题目
项目完成 50% 时挣值显示 CPI 0.9、SPI 0.9,发起人要求赶工恢复计划。你的第一步是:
EVM shows CPI 0.9, SPI 0.9 at 50% completion. The sponsor asks for a recovery plan. Your FIRST step is:
选项
- A.Perform root-cause analysis on the variances before prescribing fixes
- B.Crash the schedule immediately
- C.Request 20% more budget
- D.Replace the team
解析
解析:先诊断再治疗:对成本与进度偏差做根因分析,才能判断是赶工、重排计划还是调整范围。
Rationale:Diagnose before treating: root-cause analysis of cost and schedule variances determines whether crashing, replanning, or rescoping is appropriate.