题目
某混合项目采用预测型规划加敏捷执行。其主要好处是:
A hybrid project runs predictive planning with agile execution. The MAIN benefit is:
选项
- A.Less documentation
- B.Upfront stability for fixed constraints plus adaptive delivery where uncertainty is high
- C.Faster hiring
- D.No need for a project manager
解析
解析:混合把预测型规划(应对固定范围/预算约束)与敏捷执行(应对不确定、演进的工作)结合起来。
Rationale:Hybrid combines predictive planning (for fixed scope/budget constraints) with agile execution (for uncertain, evolving work).