战略一致性与战略对齐 · PMP 练习题解析

商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-440

题目

组织刚批准一次重大战略转向,若干在途项目已与新战略不再契合。项目组合治理机构应该怎么做?
An organisation has just approved a major strategic pivot. Several in-flight projects are now misaligned with the new strategy. What should the portfolio governance body do?

选项

  1. A.Review all in-flight projects against the new strategy, terminate or pivot misaligned projects, and reallocate resources to initiatives that support the new direction: sunk costs are irrelevant to future value decisions.
  2. B.Allow individual project managers to decide whether their projects still align with the new strategy.
  3. C.Complete all in-flight projects: sunk costs justify finishing what has been started.
  4. D.Pause all projects until the new strategy is fully detailed before making any decisions.
正确答案:A

解析

解析:A 正确。项目组合治理正是为此而存在:确保组合与组织战略保持一致。战略转向要求主动重平衡组合。沉没成本论(C)是逻辑谬误——过去的投入不能为未来的错配浪费背书;全面暂停(D)造成组织瘫痪;由各项目经理自行判断(B)缺乏组合层面的视角与权限来做这种战略级重配。 Rationale:A is correct. Portfolio governance exists precisely for this scenario: ensuring the portfolio remains aligned with organisational strategy. A strategic pivot requires active portfolio rebalancing. Sunk cost reasoning (C) is a logical fallacy: past investment doesn't justify future waste on misaligned initiatives. Pausing everything (D) creates organisational paralysis. Individual PM decisions (B) lack the portfolio-level perspective and authority for this kind of strategic rebalancing.