题目
项目初期,你希望确保整个过程中工作始终与组织战略目标保持关联。最有效的做法是什么?
Early in the project, you want to ensure the work stays connected to the organisation's strategic objectives throughout. What is the most effective practice?
选项
- A.Focus only on the schedule and budget once work begins.
- B.Trace deliverables and decisions back to the strategic objectives and business case regularly.
- C.Revisit strategy only at the final project review.
- D.Assume strategic alignment is fixed once the project is approved.
解析
解析:定期把工作回溯到目标,才能在条件变化中保持对齐,这正是价值交付的思维方式。只盯进度与预算会忘记项目存在的理由。
Rationale:Regularly tracing work back to objectives keeps the project aligned as conditions change, which is the value-delivery mindset. Focusing only on schedule and budget loses sight of why the project exists.