战略一致性与战略对齐 · PMP 练习题解析

商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-418

题目

一位高管要求参加一场昂贵的国际会议,费用记入项目预算,而该会议与项目目标毫无关系。项目经理应该怎么做?
A project manager receives a request from a senior executive to attend an expensive international conference, billed to the project budget, that has no connection to the project's objectives. What should the project manager do?

选项

  1. A.Approve the expense: senior executive requests should not be challenged.
  2. B.Politely decline to approve the charge to the project budget since it has no project-related justification, explain the project budget's purpose, and suggest an appropriate alternative funding source such as a training or executive budget.
  3. C.Approve the expense and note it in the project's risk register as a budget risk.
  4. D.Escalate to the project sponsor before making any decision.
正确答案:B

解析

解析:B 正确。项目预算只授权用于与项目相关的支出。无论请求者级别多高,批准无关支出都是资金滥用,违反 PMI 道德准则中“妥善使用项目资源”的责任。项目经理应职业地拒绝、说明理由,并指出正确的资金来源。照批(A、C)违反受托责任;一遇到就先上报(D)跳过了项目经理本人拒绝明显不当请求的职业责任。 Rationale:B is correct. Project budgets are authorised for project-related expenses only. Approving unrelated expenses, regardless of the requester's seniority, is a misuse of funds and a violation of PMI's Code of Ethics (responsibility to use project resources appropriately). The PM should decline professionally, explain why, and suggest the right funding mechanism. Approving regardless (A, C) violates fiduciary responsibility. Immediate escalation (D) skips the PM's own professional responsibility to decline a clearly inappropriate request.

同考点练习题