题目
项目经理为新 CRM 实施编制效益实现计划,主要效益写作“提升客户满意度”。作为可衡量的效益,这样写有什么问题,应如何改进?
A project manager is building the benefits realisation plan for a new CRM implementation. The primary benefit is "improved customer satisfaction." What is wrong with this as a measurable benefit and how should it be improved?
选项
- A.The benefit timeframe is missing: add "within 6 months" to make it specific.
- B.Nothing: customer satisfaction is a standard business benefit.
- C.Customer satisfaction cannot be measured. It should be replaced with a financial benefit.
- D."Improved customer satisfaction" is not measurable as stated. It should be expressed as a SMART metric: e.g., "Increase customer satisfaction score (CSAT) from 72 to 85 within 12 months of go-live, measured by quarterly survey."
解析
解析:D 正确。效益必须符合 SMART(具体、可衡量、可实现、相关、有时限)才能被管理和验证。“提升客户满意度”过于笼统——无法判断是否达成。SMART 版本明确了指标(CSAT)、基线(72)、目标(85)、时限(12 个月)与测量方式(季度调查)。客户满意度完全可以衡量(C 错);只补时间(A)仍缺少基线与目标。
Rationale:D is correct. Benefits must be SMART (Specific, Measurable, Achievable, Relevant, Time-bound) to be managed and verified. "Improved customer satisfaction" is vague: you cannot tell whether it has been achieved. A SMART version specifies the metric (CSAT), baseline (72), target (85), timeframe (12 months) and measurement method (quarterly survey). Customer satisfaction is absolutely measurable (C is wrong). Adding a timeframe alone (A) doesn't supply the missing baseline and target.