在项目整合过程中,项目经理的职责之一是:
While performing integration on the project, one of the roles of the project manager is:
选项
- A.To work with the project sponsor to understand the strategic objectives and ensure alignment of project objectives and results with those of the portfolio, program, and business areas
- B.To perform all of the work required to get the project approved and baselined for communication to the team
- C.To complete the project charter and seek formal approval from the sponsor
- D.To involve the team in group activities to facilitate teamwork, which builds an integrated project organizational structure
解析
解析:情境层面的整合意味着让项目与组织战略对齐。项目经理需与发起人合作,把项目目标与成果连接到项目组合、项目群和业务领域。
Rationale:Integration at the context level means aligning the project with organizational strategy. The project manager works with the sponsor to connect project objectives and results to the portfolio, program, and business areas.