题目
项目经理正在上线新信息系统。用户验收测试中发现 47 个缺陷:3 个致命、12 个严重、32 个轻微,上线日期在两周后。正确的优先级处理方式是什么?
A project manager is implementing a new information system. During UAT, users identify 47 defects: 3 critical, 12 major and 32 minor. The go-live date is in 2 weeks. What is the correct prioritisation approach?
选项
- A.Delay go-live by 2 months to fix all defects properly.
- B.Go live as planned and fix defects in the first post-go-live patch.
- C.Fix all 3 critical defects (go-live blockers), assess whether the 12 major defects are go-live risks or workaroundable, log all 32 minor defects for post-go-live resolution, and make a risk-based decision on the timeline with sponsor approval.
- D.Fix all 47 defects before go-live: any defect creates user dissatisfaction.
解析
解析:C 正确。按风险给缺陷排序是标准做法:阻断系统使用的致命缺陷必须上线前修复;严重缺陷需逐个评估是上线风险还是可临时规避;轻微缺陷通常登记后上线后处理。这样在质量与进度现实之间取得平衡。全部修完(D)理想但未必来得及,且轻微缺陷不足以支撑延期;为 47 个缺陷(其中 32 个轻微)推迟两个月(A)明显不成比例;带着致命缺陷上线(B)不可接受。
Rationale:C is correct. Risk-based defect prioritisation is the standard approach: critical defects that prevent system use must be fixed before go-live; major defects require case-by-case assessment of risk versus workaround; minor defects can typically be logged for later. This balances quality with schedule reality. Fixing all defects (D) is ideal but may not be time-feasible and minor defects may not justify delay. A 2-month delay (A) for 47 defects (32 of which are minor) is likely disproportionate. Going live with critical defects unfixed (B) is unacceptable.