储备分析与预算构成 · PMP 练习题解析

成本管理 简单 Process 过程域 题号 PMP202611-428

题目

项目经理正在确立项目成本基准。下列哪项包含在成本基准中,但不包含在项目预算中?
A project manager is establishing the project's cost baseline. Which of the following is included in the cost baseline but NOT the project budget?

选项

  1. A.Management reserve
  2. B.Contingency reserve
  3. C.Activity cost estimates
  4. D.Work package cost estimates
正确答案:B

解析

解析:B 正确。成本基准 = 工作包估算 + 应急储备;项目预算 = 成本基准 + 管理储备。因此应急储备在成本基准之内,而管理储备位于基准之上、由高层掌控。活动与工作包估算(C、D)是基准的基础;管理储备(A)在基准之外。 Rationale:B is correct. The cost baseline = work package estimates + contingency reserves. The project budget = cost baseline + management reserve. Therefore contingency reserves are inside the cost baseline while management reserve sits above it and is controlled by senior management. Activity and work package estimates (C, D) are the foundation of the baseline. Management reserve (A) is above the baseline, not in it.