题目
某 Scrum 团队要在冲刺评审上向 40 位相关方演示成果。Scrum Master 发现大群体动态压制了真实反馈:相关方都顺着最高级别者的意见,而不表达自己的想法。应该怎么处理?
A Scrum team is asked to demonstrate their work to 40 stakeholders at the sprint review. The Scrum Master notices that large-group dynamics are suppressing honest feedback: stakeholders are deferring to the most senior person's opinion rather than sharing their own. What should happen?
选项
- A.Continue with the large group: all stakeholders must be present for the review to be valid.
- B.Ask the senior person to withhold their opinion until last.
- C.Use structured feedback techniques (written anonymous feedback cards, small breakout groups, dot voting) to capture diverse perspectives before group discussion: preventing HiPPO effect (Highest Paid Person's Opinion) from suppressing valuable feedback.
- D.Limit sprint review attendance to 10 people maximum going forward.
解析
解析:C 正确。“最高薪者的意见”(HiPPO)效应是著名的群体动力学问题。结构化引导技术——匿名书面反馈、先小组后大会、静默贴点投票——能拉平参与度、逼出真实观点。冲刺评审的价值就在诚实、多元的反馈,结构化的做法正是在保护这一点。维持原样(A)让问题持续;硬性限人数(D)无必要地排除相关方;让领导最后发言(B)只是局部缓解,未系统性解决群体动力。
Rationale:C is correct. The HiPPO effect (suppression of individual opinion by authority) is a well-known group dynamics problem. Structured facilitation techniques, anonymous written feedback, small groups before plenary, silent dot voting, equalise participation and surface genuine perspectives. The sprint review's value is in honest, diverse feedback; structural techniques protect this. Continuing unchanged (A) perpetuates the problem. Arbitrary attendance limits (D) exclude stakeholders unnecessarily. Sequencing the senior person (B) is a partial fix but doesn't address the group dynamics systemically.