题目
项目经理正带队经历一次重大组织重组,项目结束后多数成员的汇报关系都将改变。团队士气低落、注意力涣散。优先要做什么?
A project manager is leading a team through a significant organisational restructuring that will affect most team members' reporting lines after the project ends. Team morale is low and focus is suffering. What is the priority?
选项
- A.Acknowledge the uncertainty openly and empathetically, share what information CAN be shared, advocate for the team's interests with leadership, and help individuals focus on what they can control: the project work and their professional contribution.
- B.Avoid discussing the restructuring to keep the team focused on project deliverables.
- C.Postpone project deadlines until the restructuring is resolved and uncertainty is reduced.
- D.Enforce performance standards strictly to maintain productivity during the uncertainty.
解析
解析:A 正确。不被承认的不确定性会变成谣言与焦虑。领导者坦白说明已知情况、共享可共享的信息、为团队争取利益、并帮大家把注意力放在可控之处,所带来的韧性远胜于回避或高压。严格施压(D)只会增加压力而不解决根因;回避话题(B)显得不诚实,还留下猜测空间;推迟截止日(C)往往不可行,并加重组织不稳定。
Rationale:A is correct. Uncertainty without acknowledgement becomes rumour and anxiety. A leader who openly acknowledges what is known, shares what can be shared, advocates for the team and helps people focus on what they control builds more resilience than either avoidance or enforcement. Strict performance enforcement (D) increases stress without addressing the root cause. Avoiding the topic (B) signals dishonesty and leaves a vacuum for speculation. Postponing deadlines (C) may not be possible and compounds organisational instability.