成本控制与诚信 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-423

题目

一名成员告诉 Scrum Master:自己明明在做这个 Scrum 项目,却被职能经理施压要把工时记到另一个项目代码上。Scrum Master 应该怎么做?
A team member tells the Scrum Master they are being pressured by their functional manager to log hours to a different project code, even though they are working on the Scrum project. What should the Scrum Master do?

选项

  1. A.This is a financial integrity issue. The Scrum Master should escalate to the appropriate authority (project sponsor, finance, HR) to address the misallocation of costs, and support the team member in not complying with the unethical request.
  2. B.Tell the team member to log hours to both projects to keep everyone happy.
  3. C.Tell the team member to follow their functional manager's instructions: organisational hierarchy takes precedence.
  4. D.Note the issue in the risk register and monitor for further instances.
正确答案:A

解析

解析:A 正确。故意错配项目成本属于财务造假,无论由谁提出都违反 PMI 道德准则。Scrum Master 必须通过正规渠道上报,并支持成员拒绝这一不道德要求。层级不能凌驾于道德(C);两边都记(B)加重错配;只登记风险(D)对正在发生的财务诚信违规完全不够。 Rationale:A is correct. Deliberately misallocating project costs is financial fraud. It violates PMI's Code of Ethics regardless of who is requesting it. The Scrum Master must escalate through appropriate channels and support the team member in refusing the unethical request. Hierarchy does not override ethics (C). Logging to both (B) compounds the misallocation. Risk register documentation (D) is wholly inadequate for an active financial integrity violation.