题目
敏捷教练辅导的团队已做 Scrum 半年,团队问:“流程我们都懂了,还需要 Scrum Master 吗?”最佳回应是什么?
An agile coach is working with a team that has been doing Scrum for 6 months. The team asks: "Do we still need the Scrum Master now that we know the process?" What is the best response?
选项
- A.The Scrum Master's hours can be reduced to part-time for mature teams.
- B.Yes, as the team matures, the Scrum Master's focus evolves from teaching ceremonies to coaching continuous improvement, removing organisational impediments and helping the team reach higher levels of performance and autonomy.
- C.No. Once the team knows Scrum, the Scrum Master role is no longer needed.
- D.The Scrum Master should transition to a project manager role as the team matures.
解析
解析:B 正确。Scrum Master 角色是演进而非消失。成熟团队需要的仪式引导更少,但在持续改进、组织变革以及单个冲刺无法解决的系统性障碍上需要更多辅导。Scrum Master 价值最高的工作发生在组织层面,而不是仪式层面。取消角色(C)等于拆掉持续改进的引擎;改兼职(A)或许可行,但没抓住“是重心转移而非需求消失”;转项目经理(D)混淆了两个不同角色。
Rationale:B is correct. The Scrum Master role evolves: it never disappears. A mature team needs less facilitation of ceremonies but more coaching on continuous improvement, organisational change and systemic impediments that individual sprints can't address. The highest-value Scrum Master work happens at the organisational level, not the ceremony level. Eliminating the role (C) removes the continuous improvement engine. Part-time (A) may be appropriate but misses the point that the focus shifts, not the need. PM transition (D) conflates two distinct roles.